West Rac Contr. Corp. v Huntington Vil. Hotel Partners, LLC
2022 NY Slip Op 22154 [75 Misc 3d 805]
May 16, 2022
Emerson, J.
Supreme Court, Suffolk County
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
As corrected through Wednesday, August 10, 2022


[*1]
West Rac Contracting Corp., Plaintiff,
v
Huntington Village Hotel Partners, LLC, et al., Defendants.

Supreme Court, Suffolk County, May 16, 2022

APPEARANCES OF COUNSEL

LaReddola Lester & Associates, LLP, Garden City, for defendants.

Forchelli Deegan Terrana LLP, Uniondale, for plaintiff.

{**75 Misc 3d at 806} OPINION OF THE COURT
Elizabeth H. Emerson, J.

Ordered that the motion (001) by the defendant Huntington Village Hotel Partners, LLC, for an order dismissing the complaint, vacating and discharging the notice of pendency and the mechanic's lien filed by the plaintiff, or staying the action and directing the parties to proceed to arbitration is granted to the extent of staying the action and directing the parties to proceed to arbitration; and it is [*2]further ordered that the motion (001) is otherwise denied; and it is further ordered that the motion (002) by the defendant Huntington Village Hotel Partners, LLC, for an order staying arbitration and compelling the plaintiff to litigate its claims is denied; and it is further ordered that the action is stayed and the parties are directed to proceed to arbitration in accordance with the terms of their agreement.

On October 5, 2020, the plaintiff, West Rac Contracting Corp., as the construction manager, and the defendant Huntington Village Hotel Partners, LLC (HVHP), as the owner, entered into a construction-management agreement for the construction of a hotel in Huntington, New York. The parties' agreement provides that "claims" shall be referred to the architect as the initial decision-maker, then to mediation, and to arbitration if not resolved by mediation. A "claim" is defined as a "demand or assertion by one of the parties seeking . . . payment of money, or other relief with respect to the terms of the Contract." It also includes "other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract." The plaintiff's services were terminated before the project was completed.

Between November 18 and December 2, 2021, the plaintiff filed a mechanic's lien, commenced this action to foreclose on the mechanic's lien, and filed a notice of pendency. On or about December 30, 2021, the plaintiff filed a demand for mediation with the American Arbitration Association (AAA). On January 21, 2022, HVHP moved by order to show cause to dismiss the action, to vacate and discharge the plaintiff's notice of pendency and mechanic's lien, or to stay the action and direct the parties to proceed to mediation and arbitration in accordance with the terms of their agreement. The plaintiff opposed dismissal of the action and vacatur of its mechanic's lien, but{**75 Misc 3d at 807} agreed with HVHP that the action should be stayed and the matter should proceed to arbitration. The plaintiff filed a demand for arbitration with the AAA on or about February 15, 2022. On March 11, 2022, HVHP moved by order to show cause to stay the arbitration and to compel the plaintiff to litigate its claim.

Preliminarily, the court notes that HVHP has moved both to compel arbitration of the plaintiff's claim and to stay arbitration thereof. In support of the first motion, HVHP argues that the commencement of this action was premature and in violation of the parties' agreement. HVHP argues that the action should be stayed in order for the contractual dispute-resolution procedure to be completed. In support of the second motion, HVHP argues that, by commencing this action and participating in the litigation, the plaintiff has waived its right to arbitrate.

The record reflects that the parties expressly agreed to a dispute-resolution procedure that includes arbitration, which is strongly favored in New York (see Matter of Smith Barney Shearson v Sacharow, 91 NY2d 39, 49 [1997]).

Contrary to HVHP's contentions, the plaintiff did not waive its right to arbitration by commencing this action. A plaintiff's right to file and enforce a lien under the Lien Law does not vitiate the parties' agreement to arbitrate contractual disputes (SCK Team Work Corp. v 39 Prince Realty, [*3]LLC, 2017 NY Slip Op 33410[U], *1 [Sup Ct, Queens County, Sept. 8, 2017, Butler, J.]). The commencement of an action to foreclose a mechanic's lien is in the nature of an effort to preserve the status quo pending arbitration (Allied Constr. Corp. v Parsons Transp. Group of N.Y., Inc., 74 Misc 3d 1215[A], 2022 NY Slip Op 50126[U], *1 [Sup Ct, NY County, Feb. 27, 2022, Lebovits, J.]) and does not constitute a waiver of the contractual right to resolve the dispute in arbitration (Tradesource, Inc. v Ancor, Inc., 281 AD2d 538 [2001]).

HVHP contends that the lien is void because it is facially defective pursuant to Lien Law § 19 (6), which provides that a lien may be discharged when "it appears from the face of the notice of lien that the claimant has no valid lien by reason of the character of the labor or materials furnished and for which [the] lien is claimed." HVHP contends that the lien is "grossly overstated" because it includes work that was not performed by West Rac, but by subcontractors who have already been paid. HVHP contends that West Rac is owed no more than{**75 Misc 3d at 808} $397,023.63 and that its lien in the amount of $2,876,025.07 is "overblown." This argument goes to whether the lien has been "wilfully exaggerated," not whether it is defective on its face.

Lien Law § 39 authorizes the court to declare a lien void upon finding that it has been "wilfully exaggerated" (Executive Towers at Lido v Metro Constr. Servs., 303 AD2d 545 [2003]). The court is not required to determine the validity of HVHP's claim that the lien is "wilfully exaggerated" on the basis of affidavits submitted on a motion to vacate the lien (see Matter of Upstate Bldrs. Supply Corp. [Maple Knoll Apts.], 37 AD2d 901, 902 [1971]). Whether the plaintiff deliberately and intentionally exaggerated the lien amount is a question of fact to be resolved at trial (id.; Washington 1993 v Reles, 255 AD2d 745, 747 [1998]). When, as here, there is no defect on the face of the notice of lien, any dispute regarding the validity of the lien must await the trial of the lien-foreclosure action (see Matter of Old Post Rd. Assoc., LLC v LRC Constr., LLC, 177 AD3d 658, 659 [2019]; Matter of Northside Tower Realty, LLC v Klin Constr. Group, Inc., 73 AD3d 1072 [2010]).

Lien Law § 35 provides that, if a lienor is compelled to arbitrate, the arbitrator's decision as to the value or price of labor performed and materials furnished shall be conclusive as to all parties to the arbitration in any action to foreclose the lien (Cincrete Corp. v Sansouci Realty Corp., 7 Misc 2d 717, 718 [1957]). New York courts have recognized that proceedings seeking to discharge or foreclose a mechanic's lien should be stayed pending the outcome of an arbitration to determine contractual issues such as the amount due and owing under a construction contract (Adam Devs. Enters., Inc. v Arizon Structures Worldwide, LLC, 2014 WL 4828816, *4, 2014 US Dist LEXIS 138241, *8-10 [ED NY, Sept. 29, 2014, No. 13-CV-261 (DLI)(RML), Irizarry, J.] [and cases cited therein]). Only after the arbitrator has determined the amount owed can the court determine whether the lien was "wilfully exaggerated." Accordingly, this action is stayed for the arbitrator to determine the amounts due and owing to the plaintiff, if any, under the parties' agreement.

Finally, the court finds that West Rac has capacity to maintain this action.